1. some jBPM5 - Oryx integration questions
krisverlaenen Jan 25, 2011 8:10 PM (in response to vsp)We are upgrading to the latest version of the designer. The integration code will make sure that the processes you edit in oryx are not stored in the proprietary json format (as we don't understand that) but transformed to standardized BPMN2 xml before being stored into guvnor. Note that this is still work in progress which should be completed soon.
Kris
-
2. some jBPM5 - Oryx integration questions
vsp Jan 27, 2011 5:39 PM (in response to krisverlaenen)Thanks, Kris. Two related questions:
1. will it be possible to use a custom persistence strategy, instead of the default one of storing into guvnor? For example to be able to store the BPMN XML directly into a database, so that the whole guvnor / jackrabbit etc subsystem is not required.
2. will the Oryx model <-> persistence roundtrip be possible? In other words, is there a BPMN -> JSON available as well? And will the resulting JSON be equivalent to the original, so that the model's diagram is represented in Oryx exactly as it was saved (icon locations etc)?
Thanks again,
Vlad