1. Re: JBoss EAP6 shutdown order
wdfink Jan 30, 2016 4:32 AM (in response to ramiseesniblic)Unfortunately there are some issues where the shutdown did not wait correct for every other (needed) subsystem, so it can happen that a resource is already removed but needed.
This should be solved with the 'graceful' shutdown feature of EAP7 / WildFly.
Note that you need to shutdown with a timeout to enable that feature, otherwise the shutdown behave the same as EAP6/AS7.
Could you try this (EAP7 Beta is available)?
-
2. Re: JBoss EAP6 shutdown order
ramiseesniblic Feb 4, 2016 7:06 AM (in response to wdfink)Thank you for your reply.
Unfortunately I am not in a position to upgrade currently but I beleive that I have found a work around using JBoss-cli to stop messages being delivered to the MDBs. This has, for the moment resolved the issue.