1. Re: JBPM 5.1 - BPMN and RF
salaboy21 Oct 25, 2011 1:30 PM (in response to delbacca)Hi Derek, If I don't remember wrong in the wizzard for creating a new business process, if you click next after selecting the process and writing the process name it will let you choose the runtime version. Switch to 5.1 or newer and it will create a BPMN diagram instead of RuleFlow one.
Cheers
-
2. Re: JBPM 5.1 - BPMN and RF
delbacca Oct 25, 2011 2:07 PM (in response to salaboy21)Hi Mauricio,
Thanks for your help. I did read about this business process, but i cant find the option for it when creatin a new project.
-
3. Re: JBPM 5.1 - BPMN and RF
salaboy21 Oct 25, 2011 2:13 PM (in response to delbacca)once you create a new jBPM project , inside you can create a new Business Process.
Cheers
-
4. Re: JBPM 5.1 - BPMN and RF
delbacca Oct 26, 2011 12:08 AM (in response to salaboy21)Hi Mauricio,
i have scrennshot my options, I still think i am missing the process project option. can you confirm if i am looking in the right place?
-
5. Re: JBPM 5.1 - BPMN and RF
npereira Oct 26, 2011 6:49 AM (in response to delbacca)Hello,
This is also an issue that I'm having, and I'm on jBPM 5.1. There is no option to create a BPMN.
So I just copy and paste whatever is given when the project is created!
Regards
-
6. Re: JBPM 5.1 - BPMN and RF
salaboy21 Oct 26, 2011 6:24 PM (in response to delbacca)First of all you need to create the jBPM Project that you are seeing there..
Once you get the project you need to go to the Project -> right click -> New -> Drools -> Flow File.
I'm pretty sure that will be changed in future versions.. Sorry for the confusion.. I'm not an eclipse user.
Cheers