RichFaces Team Meeting Minutes 4-30-2009

See attached transcript for details

Community

   Logo

3.3.1 release

   QA
  • Concerned about timing for CR2.
    • Proposes:
      • CR1 finish up with normal testing
      • CR2 focus on demo
      • pushing off verification of most issues to post 3.3.1 but still verifying critical issues
    Doc

        No major concerns

     Dev

         Deferred to CR/Jira talk

CR2

  • CR2 will be pushed to Monday May 4th
  • GA will be pushed to Thursday May 7th

Jira

Reviewed remaining critical issues

  • For CR2 we should resolve / defer any critical issues and most majors
  • CR2 (and really CR1) should represent releases that could go GA.