RichFaces Team Meeting Minutes 10-26-2010

Meeting Updates

  • Meetings will begin and end on time
    • Need to avoid ratholes
      • i.e. breaking down a discussion to details
      • Can be done offline
  • Start having times sections of meetings
    • Only those involved must come
    • You are responsible for coming!

4.0 Milestone4

  • Component code freeze this Friday Oct. 29th
  • Component review:
    • Select & inplaceSelect
      • Both should be ready by code freeze
      • Alex K to peer review
    • Client-Side Validation
      • Lots of open issues
      • Revisit progress at staff meeting
    • Tooltip
      • Should be done by code freeze
      • Anton to peer review
    • PanelMenu
      • Should make code freeze
      • Needs to update jira
    • FileUpload
      • Not sure can finish
      • Followup at staff
    • Calendar
      • Markhel needs to finish last 30% of server side
      • Jira needs to be updated
      • Followup at staff
    • Push Updates
      • Should be completed this week
    • Tree
      • May not make code freeze
      • Monday for bare imp
      • Followup at staff
  • General
    • Everyone should be updating jira regularly
    • When comonents are completed QE jira needs to be filled out
      • With:
        • Risks
        • Unfinished features
        • Areas to focus on
  • Jira #s
    • There are a lot of jiras open
    • Need to be reviewed for what is possible in next two weeks
  • QE