Milestone 4
- Release has been staged
- /trunk is closed for commits for now
- QE
- Status
- New issues reviewed; there are two important among them. Important issues were selected for further investigation
- Need to wait on investigation results to decide whether to re-spin release
- Discussed RF-9664 - low importance, no need to re-spin, but need mention in release notes
- Added two issues with row classes & wrong attribute name during the meeting
- Problems
- Archetypes were not tested
- Status
3.x
- Alex had question on 3.x issue - resolved
Milestone 5
- Planning JIRAs to be updated
- Update should be completed
- Meetings dedicated to a particular components discussions
- What components are necessary for discussion?
- calendar additional features
- Drop down menu
- Client-side validation
- Tree additional features
- File upload
- Drag-n-drop
- When?
- This week:
- Calendar additional features
- Drop down menu
- Client-side validation
- Next week
- The rest
- This week:
- What components are necessary for discussion?
- Questions
- None
Comments