Milestone 4
- Release plan
- No issues
- Component status
- CSV
- Ajax based in good shape
- Msg & integration needed in M5
- Jira needs to be updated
- M5 tasks to be broken out ( validators, converters, etc..)
- Some issues discussed with dynamic resource
- https://jira.jboss.org/browse/RF-9612
- Nick and Alex to take offline
- rich:objectValidator to be M5
- Ajax based in good shape
- Tooltip
- done
- Calendar
- done
- Tree
- Base functionality there
- Nick updated QE jira
- https://jira.jboss.org/browse/RF-9457
- Push
- Updated merged to trunk
- FileUpload
- Postponed, but expected early in M5 cycle
- Discussions with Konstantin to plan out
- PanelMenu
- Postponed
- Markup & skinning fixes needed
- Alex K will complete when he returns from vacation
- Postponed
- CSV
- Bug fixing this week
- Everyone has issues
- Nick and Jay to review issues
- QE Status
- Component integration started
- IDE testing waiting for post M5
JBoss tools integration
- Progress started
- Jay started integration jiras, and discussion with tools team
- Nick will discuss with Maxim
- Alex will discuss with Denis
- Ilya brought up schema integration
- Will create JBIDE jira to cover it.
- Jay started integration jiras, and discussion with tools team