    4.0.0.Milestone3

    • Respin staged
      • Lucas and Pavol looking.
      • https://jira.jboss.org/browse/RF-9417 already created. Nick will review it.
      • Nick also will review all unscheduled issues
      • Issues found before staged release reviewed and moved to M4
    • Release plan
      • QE Verification
        • Hudson builds look good.
        • Lukas and Pavol are working on metamer.
      • Release early next week
        • QE Should wrap by EOD Thursday.

     

    4.0.0.Milestone4

    • Jira review this week
      • Every one should review theirs issues.
      • Nick, Ishaikovsky and I will be reviewing future_4X, and creating the appropriate component jira's for the items plans.
    • Initial Dates:
      • Component Code Freeze Oct 26th
      • Code Freeze Nov 2nd
      • Release ~Nov 8th-9th
    • Jay will set up post mortem meeting for M3