3.3.3.GA Release
- Jira
- Release Plan
- 2 week community phase to let feedback come it, and discuss issues
- March 8th
- 1 week dev phase
- March 15th
- 1 week QE phase
- March 22nd
- Planned release date
- March 22nd
- 2 week community phase to let feedback come it, and discuss issues
- Dev
- Jira review
- JBIDE-4500 --> JBSEAM --> RF issue
- Did this make the CR1?
- QE testing it
- Concerns/questions
- QE
- Test plan
- Concerns/questions
4.0.0.Alpha2 Release
- Project plan review
- Nick and I have been working on this.
- Will be updating the wiki and blogging about plans this week
- Right now the dates are still into early/mid april
- That would put the release out to mid/late april
- Open questions, comments, concerns