3.3.3.CR1 Release
- Next 3.3.3 release will be a CR1 release
- Limited new issues found, or reported
- QE, Dev in agreement
- Release Plan
- Code Freeze Jan 29th
- Tag/Build to QE Feb 1st
- Release 15th
- May be sooner, but these are current plan
- Issue Discussion
- Note: Review priority of minor versions scheduled for CR1
- Some are not minor
- RFPL-329 - upgrade JSF to 2.0.2
- After discussion we will update to this version for testing
- RF-8204 - resolved
- RF-8213 - resolved
- RFPL issues
- QE plans to complete his items
- Dev should complete their wiki updates and other tasks
- Jay is going to discuss JOPR testing with Shelly later this week
- Timing Estimates
- See transcript Andrey outlined his estimates
- Note: Review priority of minor versions scheduled for CR1
- AI Jay: Talk with Sean at doc meeting about 3.3.3 Jiras
- Note: For 3.3.3.GA release no jiras should be assign to RF without review
4.0.0.ALPHA2 Release
- Must fill out status wiki so we can discuss in tomorrows meeting
- http://community.jboss.org/wiki/RichFaces400ALPHA2Meetings-January2010