3.3.3.BETA1 Release
- QE Status:
- Jopr Testing
- Latest Jopr has issues with other packages blocking test suite
- Jopr testsuite not blocker for release
- Will be blocker for CR1 release
- Lukas, Ondra, and Shelly will work on manual testing
- General QE Status
- A couple of JSF 2 issues found
- Under investigation but will take a little time
- Other issues also need fixing and shifted
- A couple of JSF 2 issues found
- Jopr Testing
- Discussed release options
- (1) Have a Beta 1 now and a Beta 2 mid january
- followed by CR1 and GA shortly
- Issue is limited community activity during holidays
- (2) Delay Beta 1 a week for another dev build
- QE will continue testing to check for additional issues
- Release Beta 1 before x-mas
- Have a CR1 release mid January
- Push out GA until mid-Feb to let it bake and test further
- Development will move on during this time to 4.0 and other tasks
- We chose to use the second option
- We will have a dev freeze end of week
- Build for QE Friday or weekend
- Test all next week
- Release End of week or Dec 21st at the latest
- Be ready to release Friday before.
- Dev Plan
- Andrei, and Alex will lead development and investigation
- We will meet later in week to discuss status
- (1) Have a Beta 1 now and a Beta 2 mid january
JSFSummit Review
- Part of blog post coming later